How Long Does a Kitchen Remodel Take? A Week-by-Week Timeline
By Alisher Ishankulov, owner of A-1 Renovations LLC, MHIC #110394 · Updated November 2026
A full kitchen remodel usually takes 4 to 6 weeks of work in your home once the materials are ready. Before that, plan a few weeks for design, choosing your materials and ordering cabinets. A simple kitchen refresh can be done in 1 to 2 weeks, and a remodel that moves walls or appliances can take 6 to 10 weeks.
Here is how a typical 6-week full kitchen remodel runs, week by week, so you know what to expect before the first cabinet comes out.
Before Work Starts
- Design and layout (1 to 3 weeks). We measure, draw the layout and show you renderings of the new kitchen.
- Choosing materials. You pick the cabinets, countertops, tile, flooring and lighting.
- Ordering. Cabinets are made to order, so lead times depend on the cabinet line. We confirm the delivery date before scheduling your start.
- Permits, if needed. Moving plumbing, adding circuits or removing walls needs permits, which can take several weeks to be issued.
We start demolition only when your cabinets are ready, so your kitchen is never torn out and waiting.
The 6-Week Timeline at a Glance
A typical full remodel that keeps the same layout. Every kitchen is different; your quote includes your own schedule.
Week by Week
Demolition
We protect your floors and the rest of the house, then remove the old cabinets, countertops and backsplash and haul everything away. This is also when hidden problems show up, like an old leak under the sink, so we can fix them before anything new goes in.
Plumbing and electrical updates
Outlets are brought up to today's code, wiring is run for new recessed lights, and plumbing is adjusted for the new sink and dishwasher. If this work needs a permit, the inspector checks it before the walls are closed.
Cabinets go in
The new cabinets are installed, leveled and secured. Seeing your kitchen take shape here is the exciting part of the project.
Countertops are measured and made
Countertops are measured only after the cabinets are in, so they fit exactly. The fabricator then cuts the stone, which usually takes one to two weeks. We paint the walls and ceiling while we wait.
Countertops and backsplash
The countertops are installed with the new sink, the plumbing is connected, and the backsplash tile goes up and gets grouted.
Flooring, lighting and appliances
New flooring goes down, the light fixtures are hung, your appliances are connected, and the cabinet hardware is installed.
Final details and walkthrough
We take care of the punch list, the small touch-ups that make the difference, and walk through every detail of your new kitchen with you.
How Long Each Type of Kitchen Remodel Takes
| Type of remodel | Time in your home |
|---|---|
| Refresh (refinished cabinets, hardware, paint, floor) | 1 – 2 weeks |
| Full remodel, same layout | 4 – 6 weeks |
| Full remodel with a new layout | 6 – 10 weeks |
See what each of these costs in our kitchen remodel cost guide.
What Can Slow a Kitchen Remodel Down
- Changing your mind after ordering. A new cabinet color or countertop after the order is placed restarts the lead time.
- Hidden damage. Rotten subfloor or old leaks found during demolition have to be fixed first.
- Inspections. When permits are needed, work waits for the county inspector's visit.
- Countertop fabrication. Stone can only be measured after the cabinets are in, and cutting it takes time.
Common Questions
Can I live at home during a kitchen remodel?
Yes, most of our clients do. Set up a small temporary kitchen in another room with the refrigerator, a microwave and a coffee maker. We keep the work area closed off and clean up at the end of each day.
When can I use my sink again?
Usually once the countertops are installed, around week 4 or 5 in a full remodel.
Do you give a written schedule?
Yes. Your quote includes the expected start and completion dates, and we keep you updated as the work moves along.
Ready to start planning? See our work on the kitchen remodeling in Baltimore page, or read about our remodeling process.
Plan Your Kitchen Remodel With Us
We will give you a written schedule with your quote. Tell us about your kitchen and we will call you.